Basement conversion project at a seafront hotel in Blackpool, Lancashire, UK.

Background

A 17-bedroom hotel located adjacent to the promenade had an unused basement extending under the entire footprint of the building. The basement was damp, smelly, and virtually unusable despite a previous attempt to "dry line" the walls. It is likely that the basement area was originally used as a bakery as an oven was uncovered during the conversion works which extended under the hotel car park.

The hotelier wanted to make use of the basement space to provide an additional dining area, provide a new location for the hotel bar, and provide two private bedrooms.

The Basement Conversion

Basement conversion specialists RTC of Blackpool were called in to convert the basement to the hoteliers specification. The initial work involved clearing the site of existing hardboard and timber battens which had been used to hide underlying damp problems. The project was carried out in stages to enable the owners to use parts of the basement while the conversion was in progress.

Waterproofing was achived using the Oldroyd Xv Clear cavity drainage system. An Aquadrain perimeter drainage channel leading to a sump chamber and pump was first installed around the perimeter of the basement to provide additional drainage capacity at the wall-floor junction. Oldroyd Xv membrane was then fixed to the walls using special self-sealing fixing plugs. Joins between sheets of membrane were sealed using special sealing tape. Oldroyd Xv membrane was then laid across the floor ensuring an overlap with the membrane already fixed to the walls. This system was chosen for a number of reasons:

  1. No wet trades involved - allowing basement to remain in use while works in progress.
  2. Allows waterproofing to be carried out in stages - allowing areas of the basement to continue to be used during the conversion.
  3. Suitable for application directly onto brick walls with no surface preparation

After the Oldroyd Xv membrane had been installed, wooden battens were screwed into the fixing plugs used to secure the membrane to the wall. Plasterboard was then fixed to these battens, providing a smooth finish for decorating. The gap between the plasterboard and the membrane allowed electrical and plumbing services to be hidden.

The Finished Basement

The relocation of the hotel bar to the basement provided a huge increase in dining capacity and an improvement in bar facilities.

Related Articles

More Case Studies

Visit our case studies page for a complete list of case studies available on this website.

RIBA-Approved CPD Seminars

Safeguard currently offer the following RIBA-Approved CPD Seminars free-of-charge to architects and specifiers on the UK mainland:

Basement During Conversion
Basement during conversion
 
Finished Basement Bar Area
Basement bar area
 
Finished Basement Bedroom
Completed Basement Bedroom
 
Bookmark and Share
Vandex
Oldroyd
ProBor
Dryzone

Safeguard Europe Limited provides information on this web site for your personal use. Access and use of the information is subject to the terms and conditions displayed on the site and all applicable laws. By accessing, and using information on, this web site, you accept and agree to be bound by these terms and conditions. We strongly recommend that you contact us directly for further help and guidance on all aspects of our products and services.

©Safeguard Europe Limited, Horsham, West Sussex, UK, RH13 5QL. All Rights Reserved. Registered in England and Wales. Company Number 1721203.

[Site Map]